DC-WG: operating points

Mark Hahn (mhahn@cadence.com)
Mon, 19 Apr 1999 14:12:03 -0700

This is a summary of the constraints and environment
conditions for the timing domain that should support values
for both minimum and maximum operating points.

I've used a hybrid of the terminology from the current
taxonomy, the strawman, GCF, and the DCDL subset.

1. borrow_limit
2. clock_arrival_time
3. clock_common_delay
4. clock_delay
5. clock_required_time
6. clock_uncertainty
7. data_arrival_time
8. data_required_time
9. derived_waveform
10. drive_cell
11. drive_resistance
12. external_delay
13. operating_conditions
14. path_delay
15. port_capacitance
16. port_capacitance_limit
17. port_wire_load_model
18. slew_time
19. slew_time_limit
20. tree_delay
21. wire_load_model

Thanks,
Mark

Thanks,
Mark

-- 
Mark Hahn                                          phone: (408) 428-5399
Senior Architect                                   fax:   (408) 428-5959
Cadence Design Systems                             email: mhahn@cadence.com