TRCE: How to analyze (the longest) nets/paths in timing constraints


Record #2740

Product Family: Software

Product Line: FPGA Implementation

Product Part: trce

Problem Title:
TRCE: How to analyze (the longest) nets/paths in timing constraints


Problem Description:
Urgency: Standard

General Description:
You can enter timing constraints to tell the place and route
software the maximum period you want on some pieces of logic
and the minimum delay that you want on other pieces of logic.
How can you analyze the path delays for a timing constraint?
The bottom of the solution describes how to find the longest
path for a timing constraint.




Solution 1:

Timing Reports:

   Report Browser:

     The Report Browser contains 2 timing reports:
        - Logic Level Timing Report
        - Post Layout Timing Report

     The Logic Level Timing Report is produced after the Map stage. The
     times reported are based on the actual block delays and estimates
     for the route delays.

     The Post Layout Timing Report is produced after the Place and
     Route stage. The times reported here are based on real block and
     real route delays.

     To enable either report to give an analysis of the paths within
     timing constraints:

      1. In the Design Manager, select the revision that you are
         analyzing.

      2. Click on the Flow Engine button and from the Flow Engine
         menu, select Setup->Options.

      3. In the Options dialog, click on the Edit Template button
         for the Implementation Template.

      4. On the Implementation Template, click on the Timing Tab.
         Make sure that **Report Paths in User Timing Constraint**
         is selected.

     NOTE: The Logic Level Timing Report and Post Layout Timing Report
        are not produced by default. In order to produce the reports:

      1. In the Design Manager, select the revision that you are
         analyzing.

      2. Click on the Flow Engine button and from the Flow Engine
         menu, select Setup->Options.

      3. In the Options dialog, select Produce Logic Level Timing
         Report to enable the Flow Engine to create the Logic Level
         Timing Report. Select Produce Post Layout Timing Report
         to enable the Flow Engine to create the Post Layout Timing
         Report. Click on OK to save the settings.

      4. The Flow Engine will produce the Logic Level Timing
         Report in the Map stage if the Produce Logic Level Timing
         Report option is set. The Flow Engine will produce the
         Post Layout Timing Report in the Timing stage if the
         Produce Post Layout Timing Report option is set.

   Command Line:

      A post Map path analysis of timing constraints report can be
      generated by running the following command:

         trce <design name>.ncd <design name>.pcf -v -o <design name>.twr

          - where <design name>.ncd and <design name>.pcf are
               the output of map

          - The timing constraint report will be in <design name>.twr

      A post place and route timing constraint report can be generated
      by running the following command:

         trce <design name>.ncd <design name>.pcf -v -o <design name>.twr

          - where <design name>.ncd and <design name>.pcf are
               the output of par

          - The timing constraint report will be in <design name>.twr


Sample of a Path Analysis Timing Constraint Report:

======================================================================
Timing constraint: NET "I0/CLK" PERIOD =  25 nS   HIGH 50.000 % ;
 1789 items analyzed, 0 timing errors detected.
 Minimum period is  20.692ns.
----------------------------------------------------------------------
Slack:	   4.308ns path I0/LCAD07 to I0/RR15//QX relative to
	  25.000ns delay constraint

Path I0/LCAD07 to I0/RR15//QX contains 4 levels of logic:
Path starting from Comp: P141.PAD
To		     Delay type 	Delay(ns)  Physical Resource
						   Logical Resource(s)
-------------------------------------------------  --------
P141.I1 	     Tpid		   1.180R  I0/LCAD07
						   I0/LCAD07
						   I0/LCA07
CLB_R12C14.F2	     net		   8.776R  I0/LCA07
CLB_R12C14.Y	     Tiho		   2.140R  I2/N$2726//G
						   I2/N$2726//G
						   I2/N$1978//F
TBUF_R7C10.2.T	     net		   5.650R  I2/N$1978//F
TBUF_R7C10.2.O	     Ton		   0.800R  I2/TBUF_EJ_2
CLB_R7C9.G2 net 1.237R I2/DATIN1<5>
Tick 0.909R I0/RR15//QX
                                  I0/RR15//G
                                  I0/RR15//QY
-------------------------------------------------
Total (24.3% logic, 75.7% route) 20.692ns (to I0/CLK)



For each timing constraint, the report will list all of the paths,
starting from worst case path to best case path. As shown above,
every path will have its subpaths enumerated. The sample above
only shows enumeration for the worstcase path in timing constraint:

   NET "I0/CLK" PERIOD = 25 nS

This path starts as input at Pad 141. It travels to the F function
generator of CLB R12C14. It then enters the tri-state input
of a tri-state buffer next to CLB R7C10. It then enters the G
function generator of CLB R7C9 (a neighbor of R7C10) and includes
the setup times for both flip flops (QX and QY) in R7C9.

To find delays on a specific net, in the text editor, search for
the net name.

NOTE: The R on the delays refers to Rising.




End of Record #2740 - Last Modified: 05/28/99 09:03