Implementation

Given an activity-node graph, the objective of critical path analysis is to determine the slack time for each activity and thereby to identify the critical activities and the critical path. We shall assume that the activity node graph has already been transformed to an edge-node graph. The implementation of this transformation is left as a project for the reader (Project gif). Therefore, the first step is to compute the earliest and latest event times.

According to Equation gif, the earliest event time of vertex w is obtained from the earliest event times of all its predecessors. Therefore, must compute the earliest event times in topological order. To do this, we define the EarliestTimeVisitor shown in Program gif.

   program54942
Program: Critical path analysis--computing earliest event times.

The EarliestTimeVisitor has one field, earliestTime, which is an array used to record the tex2html_wrap_inline71817 values. The visit method of the EarliestTimeVisitor class implements directly Equation gif. It uses an getIncidentEdges enumeration to determine all the predecessors of a given node and computes tex2html_wrap_inline71875.

In order to compute the latest event times, it is necessary to define also a LatestTimeVisitor. This visitor must visit the vertices of the event-node graph in reverse topological order. Its implementation follows directly from Equation gif and Program gif.

Program gif defines the method called criticalPathAnalysis that does what its name implies. This method takes as its argument a Digraph that represents an event-node graph. This implementation assumes that the edge weights are instances of the Int class defined in Program gif.

   program54969
Program: Critical path analysis--finding the critical paths.

The method first uses the EarliestTimeVisitor in a topological order traversal to compute the earliest event times which are recored in the earliestTime array (lines 7-10). Next, the latest event times are computed and recorded in the latestTime array. Notice that this is done using a LatestTimeVisitor in a postorder depth-first traversal (lines 12-15). This is because a postorder depth-first traversal is equivalent to a topological order traversal in reverse!

Once the earliest and latest event times have been found, we can compute the slack time for each edge. In the implementation shown, an edge-weighted graph is constructed that is isomorphic with the the original event-node graph, but in which the edge weights are the slack times as given by Equation gif (lines 17-30). By constructing such a graph we can make use of Dijkstra's algorithm find the shortest path from start to finish since the shortest path must be the critical path (line 31).

The DijkstrasAlgorithm method given in Section gif returns its result in the form of a shortest-path graph. The shortest-path graph for the activity-node graph of Figure gif is shown in Figure gif. By following the path in this graph from vertex 9 back to vertex 0, we find that the critical path is tex2html_wrap_inline71877.

   figure54986
Figure: The critical path graph corresponding to Figure gif.