Hi All,
In today's P1800 meeting we discussed the purpose of the Scope document on which
we have been working. It was decided that:
- The document is non-binding; we will not delay the release of the LRM because
we have not completed all of the tasks we put in the Scope document. Nor are
we going to be limited to the tasks contained in the Scope document. If a
more pressing issues arises, we will be able to address it.
- We need to formulate our list of high priority items given the timeline that
has already been established. Specifically, we need to complete our work by
October 2011. Given that the other committees will be completing tasks at
roughly the same time, the SV-CC committee will need to leave a few months
at the end to react to the other committee's enhancements. Therefore, I would
suggest that we give ourselves a deadline of August 2011.
Hopefully, this information will facilitate our effort to produce a good Scope
document.
-Chas
-- Charles Dawson Senior Engineering Manager NC-Verilog Team Cadence Design Systems, Inc. 270 Billerica Road Chelmsford, MA 01824 (978) 262 - 6273 chas@cadence.com -- This message has been scanned for viruses and dangerous content by MailScanner, and is believed to be clean.Received on Thu May 13 14:15:42 2010
This archive was generated by hypermail 2.1.8 : Thu May 13 2010 - 14:15:48 PDT