Hi Karen,
For some reason, the mantis data base is not allowing me to do 6.1.2
as described below. I set the status to "new" and it puts it into
"assigned".
-Chas
-------- Original Message --------
Subject: [sv-cc] Schedule and process for reviewing incorporated Items
Date: Fri, 14 Jan 2005 11:51:14 -0500
From: Charles Dawson <chas>
Reply-To: chas
To: SV-CC <sv-cc@eda.org>
Hi All,
According to the last schedule that I have, we need to have all of our Items
that have been incorporated into the latest draft reviewed by Feb 3, 2005.
Please plan accordingly. Below I have extracted the instructions Karen
published for this phase of the operation:
6. LRM Review by the SV-* Committees
1. Once an issue has status:acknowledged, the appropriate SV-* committee must
review the changes for correctness
1. If the change is correct, the issue is moved to status:closed
2. If the change is not correct and the description was correct, the issue is
moved to category:SV-LRM and status:new, and mail is sent to the LRM team
3. If the change is not correct and the description of the change needs to be
modified, the issue is changed to status:assigned
Please let me know if you have any questions. Thanks.
-Chas
-- Charles Dawson Senior Engineering Manager NC-Verilog Team Cadence Design Systems, Inc. 270 Billerica Road Chelmsford, MA 01824 (978) 262 - 6273 chas@cadence.com -- Charles Dawson Senior Engineering Manager NC-Verilog Team Cadence Design Systems, Inc. 270 Billerica Road Chelmsford, MA 01824 (978) 262 - 6273 chas@cadence.comReceived on Wed Jan 19 13:07:12 2005
This archive was generated by hypermail 2.1.8 : Wed Jan 19 2005 - 13:07:27 PST